Deployment & Operations

Scheduled Maintenance Program

A tiered schedule groups tasks into short online checks and longer outages timed to component life and inspection needs.

The scheduled maintenance program groups tasks by frequency and by whether they can be done while running. Frequent, low-impact checks are done online; deeper inspections and replacements are batched into planned outages so the machine comes down as few times as possible for as short a time as possible.

MAINTENANCE TIERSOnline checksdaily / weekly, no shutdownMinor outageinstrument + aux serviceMajor outagecomponent inspection / replaceLife-drivenplug / first-wall campaigns

Task tiers

Outage batching

Because breaking vacuum and warming coils are expensive in time, tasks that require those conditions are batched. An outage is planned so that once the machine is opened, all the work that needs that access is completed together, followed by pump-down, bakeout, and conditioning to return to service.

Planning inputs

The schedule is built from component life estimates, inspection intervals, and condition-monitoring data. It is engineered at design stage against the frozen machine and refined as operating experience accumulates, beginning with the first test burner.

Content reviewed August 2026 · design-and-simulation stage