The Machine

Plug Coil Stress Gate

As specified, the coil structure to hold 26.49 T over the plug bore is overstressed by roughly 3–3.9x; the plug is infeasible exactly as drawn.

This is one of the four honest gates on the burner (Aegis / MetroVolt), stated as a design-and-simulation finding. The plug demands 26.49 T over a plasma-relevant bore. Magnetic forces on a coil scale with the square of the field, and at 26.49 T the hoop and radial loads exceed what the specified conductor-and-structure package can carry by a factor of roughly 3 to 3.9.

Put plainly: the plug coil as currently specified would be overstressed. It is not a marginal exceedance to be trimmed with a safety-factor argument; it is a multiple. The burner cannot be built to this drawing, and the design does not pretend otherwise.

Plug coil stress vs. feasible structural limitfeasible / demonstratedrequired ≈ 3–3.9× the feasible limit as specifiedOverstressed by a multiple, not a margin — infeasible as drawn

What the gate does not mean

Paths that could close it

Closing the gate means changing the specification, the materials, or the geometry until the stress falls to feasible levels: higher-strength structural materials, graded or nested winding that redistributes load, a smaller bore, a lower plug field paired with a different confinement scheme, or stress-managed conductor architectures. Each path changes the machine and must be re-simulated. None is demonstrated today.

Stating this gate at full candor is deliberate. A burner design that hid a 3–3.9x structural overstress would not be trustworthy. The number is reported so the engineering problem is visible and specific.

Content reviewed August 2026 · design-and-simulation stage